Route 63 Rehabilitation Route 63 Rehabilitation
Route 63 Rehabilitation

Updates - Sept. 24, 2008
 

Randolph County

Semi-final inspection complete. Contractor is working on corrections.

 

Adair and Macon Counties

All surfacing is complete. Remaining work consists of striping and seeding. Re-decking of the railroad bridge at La Plata began July 14. Bridge work expectetd to be complete by late October.

 

Macon County

Work started on July 31. All work on southbound lane is complete. Diamond grinding of the northbound lane is planned to begin Sept. 26. Work expected to be complete by mid-October.

 

Adair County

Contract has been awarded to W.L. Miller. Contractor will begin early spring 2009.