Adair County
Construction Projects:
US 63 - Drainage and sidewalk improvements in Kirksville
Work Zone Info: Inactive
Project Status: 0% complete- Preconstruction conference to be scheduled to determine work schedule.
Estimated Completion: Fall 2012
Macon Project Office-Resident Engineer Jeff Gander
Maintenance
Route J, T, Y, & BB – May 24-25 pavement repairs; traffic may be reduced to one lane
Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.
Audrain County
Construction Projects:
Route JJ - Resurface from US 54 at Mexico to the end of state maintenance .
Work Zone Info: Inactive
Project Status: 0% complete-Resurfacing to begin in June.
Estimated Completion: Summer 2012
Macon Project Office-Resident Engineer Jeff Gander
Route B - Resurface from US 54 through Rush Hill to Route J.
Work Zone Info: Inactive
Project Status: 0% complete-Resurfacing to begin in June.
Estimated Completion: Summer 2012
Macon Project Office-Resident Engineer Jeff Gander
Route KK - Resurface from MO 19 at Laddonia to Route B north of Rush Hill.
Work Zone Info: Inactive
Project Status: 0% complete-Resurfacing to begin in June.
Estimated Completion: Summer 2012
Macon Project Office-Resident Engineer Jeff Gander
MO 19 - Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles.
Work Zone Info: Inactive
Project Status: 0% complete- Inactive
Estimated Completion: Summer 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Maintenance
Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.
Clark County
Construction Projects
MO 81 - Safe and Sound Bridge replacement at Fox River north of Kahoka
Work Zone Info: ROAD CLOSED detour over Routes C, B and US 136.
Project Status: 80% complete-Working on laying asphalt approaches and pouring barrier walls.
Estimated Completion: May 24, 2012
Macon Project Office-Resident Engineer Jeff Gander
Route D - Safe and Sound Bridge replacement at Little Wyaconda River east of Fairmont
Work Zone Info: ROAD CLOSED detour over Routes W and A .
Project Status: 65% complete-Working on laying asphalt approaches and pouring barrier walls
Estimated Completion: May 30, 2012
Macon Project Office-Resident Engineer Jeff Gander
Route D - Safe and Sound Bridge replacement at Wyaconda River south of Kahoka - Bridge to close May 29, 2012 for 58 days
Work Zone Info: Inactive - Road to be closed May 29 with detour over Routes 81, M and Lewis Route E
Project Status: 0% complete- Bridge to close for demolition May 29, weather permitting.
Estimated Completion: July 20, 2012
Macon Project Office-Resident Engineer Jeff Gander
Maintenance
Route HH – May 24 traffic reduced to one lane for pavement repairs from 8 a.m. to 3 p.m. from Route Y south to the end of State Maintenance; traffic reduced to one lane from 8 a.m. to 3 p.m.
Various Routes - May 24-25 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Knox County
Construction
Route M - Safe and Sound Bridge replacement at Middle Fabius River south of Rutledge near the Community of Millport - Bridge to close for 58 days
Work Zone Info: Inactive - Road to be closed June 19 with detour over Routes V and K
Project Status: 0% complete- Demolition begins June 19, weather permitting.
Estimated Completion: August 8, 2012
Macon Project Office-Resident Engineer Jeff Gander
Maintenance
Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone
Lewis County
Construction
MO 16 - Safe and Sound Bridge replacement at Sugar Creek east of Monticello - Bridge to close June 5, 2012 for 49 days
Work Zone Info: Inactive - Road to be closed June 5 with detour over Routes F, E and A
Project Status: 0% complete- Bridge to close for demolition June 5, weather permitting.
Estimated Completion: July 23, 2012
Macon Project Office-Resident Engineer Jeff Gander
Maintenance
Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.
Lincoln County
Construction Projects
MO 79 - Bridge project at Sandy Creek 1 mile north of Route Y at Foley
Work Zone Info: Road to close July 15
Detour Local and Tourist Traffic on Routes Y, W and B
Detour Option Commercial Traffic on MO 47, US 61 and Route B
Project Status: 0% complete-
Road to be closed from July 15-Oct. 1
Estimated Completion: October 2012
Troy Project Office-Resident Engineer Rick Domzalski
MO 47 - Resurface driving lanes and shoulders from west of Route J to Main St. in Troy
Work Zone Info: Nighwork 8 p.m. to 5 a.m. with one lane traffic and flaggers
Project Status: 0% complete- Resurfacing in progress.
Estimated Completion: end of June 2012
Troy Project Office-Resident Engineer Rick Domzalski
US 61 - Resurface northbound lanes and shoulders from just north of Route Z to just south of Route K, 9.5 miles
Work Zone Info: Inactive - One lane traffic beginning June 22-July 31.
Project Status: 0% complete- Milling operations June 22-July 12; paving operations for July 13-July 31.
Estimated Completion: August 9
Troy Project Office-Resident Engineer Rick Domzalski
US 61 - Pavement repair and resurfacing north and southbound lanes from just north of Route OO in Pike Co. to Route B in Lincoln Co., 13.2 miles
Work Zone Info: Inactive - One lane traffic beginning June 5-July 3.
Project Status: 0% complete- Milling operations June 5-12; paving operations scheduled for June 13-20.
Estimated Completion: July 3
Troy Project Office-Resident Engineer Rick Domzalski
Route A - Seal coat from Route DD to Interstate 70 in Warren Co., 12.9 miles
Work Zone Info: Inactive - One lane traffic May 30-June 1.
Project Status: 0% complete-Seal coat begins May 30-June 1.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route JJ - Seal coat from Route W south junction to MO 79, 8 miles
Work Zone Info: Inactive - One lane traffic June 13-14.
Project Status: 0% complete-Seal coat begins June 13-14.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route B - Seal coat from US 61 to MO 79, 10.2 miles
Work Zone Info: Inactive - One lane traffic June 15-19.
Project Status: 0% complete-Seal coat begins June 15-19.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route OO - Seal coat from Route C to end of state maintenance near Chain of Rocks, 1.8 miles
Work Zone Info: Inactive - One lane traffic May 31 - June 1.
Project Status: 0% complete-Seal coat begins May 31-June 1.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Maintenance
Route U – May 24-25 traffic reduced to one lane for pavement repairs from 8 a.m. to 4 p.m. from US 61 south of Moscow Mills to MO 47 south of Hawk Point
Route AA – May 29 traffic reduced to one lane for pavement repairs from 8 a.m. to 4 p.m. from MO 47 between Hawk Point and Troy north to the end of State Maintenance
MO 47 - May 29-30 traffic reduced to one lane for pavement repairs from 8 a.m. to 4 p.m. from just west of US 61 at Troy west to Hawk Point
Route D - May 31 traffic reduced to one lane for pavement repairs from 8 a.m. to 4 p.m. from Route O at Olney to Route E
Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.
Macon County
Maintenance
Route 36 & 63 – May 24-25 mowing; traffic reduced to one lane, 6:30 a.m. to 5:00 p.m.
Marion County
Construction
MO 168 – Bridge replacement over North River 1.4 miles west of Route C near Palmyra.
Work Zone Info: ROAD CLOSED. Detour over Routes C, Z and 168
Project Status: 5% complete - Demolition of old bridge continues and will work on coring drilled shafts.
Estimated Completion: fall 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
US 24/61 Palmyra – Intersection improvements at Palmyra from Main Cross St. to Thompson St.
Work Zone Info: Inactive. One lane traffic through work zone area.
Project Status: 0% complete - Inactive. Project has not been scheduled.
Estimated Completion: October 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Maintenance
Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.
Monroe County
Construction Projects
Routes 107 and FF - Preventative maintenance on Mark Twain Lake bridges over North Fork and South Fork Salt River on Route 107, and North Fork Salt River Bridge on Route FF; substructure repairs and modifications, expansion joint replacement, removal and replacement of asphalt surface and upgrading the existing guardrail. Contractor- PCI Roads, LLC.
Project Status: 89% complete - OPEN TO TRAFFIC with one lane traffic on MO 107 for painting and asphalt work at various times.
Macon Project Office-Resident Engineer Jeff Gander
Route CC - Safe and Sound Bridge replacement at Clear Creek south of Shelbina
Project Status: COMPLETED - OPEN TO TRAFFIC
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
US 24 - Resurface driving lanes from Randolph County line to just east of Route 15 near Paris
Work Zone Info: One lane traffic
Project Status: 11% complete-Resurfacing with one lane traffic near Paris.
Estimated Completion: Summer 2012
Macon Project Office-Resident Engineer Jeff Gander
Maintenance:
Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.
Montgomery County
Construction Projects:
MO 161 - Safe and Sound Bridge replacement at Elkhorn Creek east of Montgomery City - Bridge to close May 21, 2012 for 49 days
Work Zone Info: Inactive - Road to be closed May 21 with detour over MO 19 and Route CC.
Project Status: 0% complete- Road to be closed at bridge May 21 for demolition to begin, weather permitting.
Estimated Completion: July 9, 2012
Troy Project Office-Resident Engineer Rick Domzalski
MO 94 – Seal coat from MO 19 to Route T at Augusta near the Warren/St. Charles Co. line, 32.670 miles.
Work Zone Info: Inactive -One lane traffic
Project Status: 0% complete-Seal coat to be scheduled at a later date.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route K – Seal coat from Route D in Callaway County to the Montgomery County line, 5.885 miles.
Work Zone Info: Inactive - One lane traffic
Project Status: 0% complete-Seal coat to be scheduled at a later date.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route D – Seal coat from I-70 at Williamsburg in Callaway County to MO 94 east of Portland near the Montgomery County line, 18.336 miles.
Work Zone Info: Inactive - One lane traffic
Project Status: 0% complete-Seal coat to be scheduled at a later date.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Maintenance
Various Routes - May 24-25 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone
Pike County
Construction Projects:
Route D - Safe and Sound Bridge replacement at Little Calumet Creek just south of Route N near Calumet - Bridge to close May 7, 2012 for 58 days
Work Zone Info: ROAD CLOSED with detour over MO 79 and Routes N, W and WW.
Project Status: 10% complete- Contractor plans to pour footings and columns on the intermediate bents, weather permitting.
Estimated Completion: June 30, 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
US 54 - Safe and Sound Bridge replacement at Noix Creek between Bowling Green and Louisiana- Bridge to close June 18, 2012 for 50 days
Work Zone Info: Inactive - June 18 road to be closed
Commercial Vehicle Detour - Recommended Detour Routes over US 54, MO 79 south, Route B west, US 61 North or South
Local and Tourism Detour - Recommended Detour Routes over US 54, Route UU, US 61 North or South
Project Status: 0% complete- Road to be closed at bridge June 18 for demolition to begin, weather permitting.
Estimated Completion: August 7, 2012
Troy Project Office-Resident Engineer Rick Domzalski
US 54 - Safe and Sound Bridge replacement at North Fork of Noix Creek between Bowling Green and Louisiana- Bridge to close June 25, 2012 for 40 days
Work Zone Info: Inactive - June 25 road to be closed
Commercial Vehicle Detour - Recommended Detour Routes over US 54, MO 79 south, Route B west, US 61 North or South
Local and Tourism Detour - Recommended Detour Routes over US 54, Route UU, US 61 North or South
Project Status: 0% complete- Road to be closed at bridge June 25 for demolition to begin, weather permitting.
Estimated Completion: August 4, 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route UU - Resurface from US 61 near Bowling Green to US 54 near Louisiana
Project Status: COMPLETED - ALL LANES OPEN TO TRAFFIC
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
MO 79 - Seal coat from Ralls County line to Route TT near Ashburn.
Work Zone Info: Inactive - Work tentatively scheduled to begin after May 1.
Project Status: 0% complete- Inactive
Estimated Completion: Summer 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Route Z - Seal coat from
Route 161 to US 61 in Pike and Lincoln Counties, 16.9 miles
Work Zone Info: Inactive - One lane traffic May 23-31.
Project Status: 0% complete-Seal coat begins May 23 thru 31.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route H - Seal coat
from Route W south junction to MO 79, 3.9 miles
Work Zone Info: One lane traffic May 22.
Project Status: 0% complete-Seal coat begins May 22.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
US 61 - Pavement repair and resurfacing north and southbound lanes from just north of Route OO in Pike Co. to Route B in Lincoln Co., 13.2 miles
Work Zone Info: Inactive - One lane traffic beginning June 12.
Project Status: 0% complete- Milling and paving operations scheduled to begin June 12.
Estimated Completion: July 3
Troy Project Office-Resident Engineer Rick Domzalski
Maintenance
Various Routes - May 24-25 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Ralls County
Construction Projects:
MO 19 - Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles.
Work Zone Info: Inactive - Job has not been scheduled
Project Status: 0% complete- A preconstruction conference will be scheduled to determine the start date.
Estimated Completion: Summer 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Route T - Resurface from just south of MO 79 to Route N south of Hannibal .
Work Zone Info: Inactive - Work tentatively scheduled to begin June 1.
Project Status: 0% complete- Inactive
Estimated Completion: Fall 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
MO 154 - Resurface from MO 19 to US 54 near Hutchison between Curryville and Vandalia.
Work Zone Info: Inactive
Project Status: 0% complete-Resurfacing to begin in June.
Estimated Completion: Summer 2012
Macon Project Office-Resident Engineer Jeff Gander
Route E - Seal coat from MO 79 to end of State maintenance near Saverton.
Work Zone Info: Inactive - Work tentatively scheduled to begin after May 1.
Project Status: 0% complete- Inactive
Estimated Completion: Summer 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Route T - Seal coat from Route N south of Hannibal to MO 79 near Ashburn .
Work Zone Info: Inactive - Work tentatively scheduled to begin June 1.
Project Status: 0% complete- Inactive
Estimated Completion: Summer 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Route V - Seal coat from Ralls Street in New London to Route T.
Work Zone Info: Inactive - Work tentatively scheduled to begin after May 1.
Project Status: 0% complete- Inactive
Estimated Completion: Summer 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Route N - Seal coat from Route T to MO 79 near Saverton.
Work Zone Info: Inactive -Work tentatively scheduled to begin after May 1.
Project Status: 0% complete- Inactive
Estimated Completion: Summer 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Maintenance
Various Routes - May 24-25 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Randolph County
Construction Projects
Route B - Resurfacing from Route A to US 63 near Clark, 8.541 miles
Work Zone Info: One lane traffic with 45 mph work zone speed limit from 6:30 a.m. to 8 p.m.. while crews are present.
Project Status: 64% complete-Paving operation to begin May 22 or 23.
Estimated Completion: Summer 2012
Macon Project Office-Resident Engineer Jeff Gander
Route M - Resurfacing from US 63 in Moberly to MO 151 at the Monroe county line, 10.869 miles
Work Zone Info: One lane traffic with 45 mph work zone speed limit from 6:30 a.m. to 8 p.m.. while crews are present.
Project Status: 64% complete-Paving operations in progress.
Estimated Completion: Summer 2012
Macon Project Office-Resident Engineer Jeff Gander
MO 3 - Resurfacing from Route T to north of US 24 near Clifton Hill, 12.721 miles
Project Status: COMPLETED-ALL LANES OPEN TO TRAFFIC
Macon Project Office-Resident Engineer Jeff Gander
Maintenance
Route AA – May 24-25 extensive pavement repairs; traffic reduced to one lane from Rte B to Rte A, 7:00 a.m. to 3:30 p.m.
Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.
Schuyler County
Maintenance
Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.
Scotland County
Maintenance
Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.
Shelby County
See Route 36 Four-Lane Webpage
Construction Projects:
Route H - Safe and Sound Bridge replacement at Hilton Branch south of Leonard - Bridge to close May 7, 2012 for 39 days
Work Zone Info: ROAD CLOSED with detour over MO 151 and Route K .
Project Status: 50% complete- Contractor plans to grout, post tension and possibly pour barrier wall, weather permitting.
Estimated Completion: May 30, 2012
Macon Project Office-Resident Engineer Jeff Gander
MO 151 - Safe and Sound Bridge replacement at Otter Creek south of Clarence - Bridge to close May 31, 2012 for 45 days
Work Zone Info: Inactive - Road to be closed May 31 with detour over US 36, and Routes TT and DD .
Project Status: 0% complete- Road to be closed at bridge May 31 for demolition to begin, weather permitting.
Estimated Completion: July 15, 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
MO 15 – Install guardrail near Elm Street at US 36 interchange at Shelbina
Work Zone Info: Inactive. One lane traffic through work zone area.
Project Status: 0% complete - Inactive. Project has not been scheduled.
Etimated Completion: October 2012
Macon Project Office-Resident Engineer Jeff Gander
Maintenance
Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.
Warren County
Construction Projects:
Route A - Safe and Sound Bridge replacement at Camp Creek east of Truxton
Work Zone Info: ROAD CLOSED detour over MO 47 and Routes W and A.
Project Status: 80% complete-Contractor plans to work on barrier curbs and place guardrail and finish dirt work, weather permitting.
Estimated Completion: May 25, 2012
Troy Project Office-Resident Engineer Rick Domzalski
I-70 eastbound – Resurface driving lanes and shoulders from the St. Charles Co. line to Wright City
Work Zone Info: Night work with one lane traffic from 7 p.m. to 5 a.m.
Project Status: 0% complete- Resurfacing in progress.
Estimated Completion: July 2012
Troy Project Office-Resident Engineer Rick Domzalski
MO 94 – Seal coat from MO 19 to Route T at Augusta near the Warren/St. Charles Co. line, 32.670 miles.
Work Zone Info: Inactive - One lane traffic
Project Status: 0% complete-Seal coat to be scheduled at a later date.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route MM - Resurface from Old 40 to Route M at Warrenton
Work Zone Info: Inactive
Project Status: 0% complete- Milling and resurfacing operations to be scheduled at a later date.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route AA - Resurface from Route 47 to the end of state maintenance
Work Zone Info: Inactive
Project Status: 0% complete- Milling and resurfacing operations to be scheduled at a later date.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route H - Seal coat from just south of I-70 to Route M, 3.6 miles
Work Zone Info: Inactive - One lane traffic June 4.
Project Status: 0% complete-Seal coat begins June 4.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route W- Seal coat from Warrenton north to Route A, 10.2 miles
Work Zone Info: Inactive -One lane traffic
Project Status: 0% complete-Seal coat to be scheduled at a later date
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Maintenance
Route N – May 24 traffic reduced to one lane for pavement repairs from 8 a.m. to 4 p.m. from MO 47 to MO 94 at Treloar
Route CC – May 29 traffic reduced to one lane for pavement repairs from 8 a.m. to 4 p.m. from MO 47 south of Warrenton to the end of State Maintenance
Route F – May 30 traffic reduced to one lane for pavement repairs from 8 a.m. to 4 p.m. from Wright City to the end of State Maintenance near Innsbrook
Various Routes - May 24-25 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
|