All road work listed below is subject to change due to weather or priority adjustments.

Adair County

Construction Projects:

US 63 - Drainage and sidewalk improvements in Kirksville

Work Zone Info: Inactive

Project Status: 0% complete- Preconstruction conference to be scheduled to determine work schedule.

Estimated Completion: Fall 2012
Macon Project Office-Resident Engineer Jeff Gander


Maintenance

Route J, T, Y, & BB  – May 24-25 pavement repairs; traffic may be reduced to one lane

Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.

Back to Top

Audrain County

Construction Projects:

Route JJ - Resurface from US 54 at Mexico to the end of state maintenance .

Work Zone Info: Inactive

Project Status: 0% complete-Resurfacing to begin in June.

Estimated Completion: Summer 2012

Macon Project Office-Resident Engineer Jeff Gander

Route B - Resurface from US 54 through Rush Hill to Route J.

Work Zone Info: Inactive

Project Status: 0% complete-Resurfacing to begin in June.

Estimated Completion: Summer 2012

Macon Project Office-Resident Engineer Jeff Gander

Route KK - Resurface from MO 19 at Laddonia to Route B north of Rush Hill.

Work Zone Info: Inactive

Project Status: 0% complete-Resurfacing to begin in June.

Estimated Completion: Summer 2012

Macon Project Office-Resident Engineer Jeff Gander

MO 19 - Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles.

Work Zone Info: Inactive

Project Status: 0% complete- Inactive

Estimated Completion: Summer 2012

Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln

Maintenance

Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.

Back to Top

Clark County

Construction Projects

MO 81 - Safe and Sound Bridge replacement at Fox River north of Kahoka

Work Zone Info: ROAD CLOSED detour over Routes C, B and US 136.

Project Status: 80% complete-Working on laying asphalt approaches and pouring barrier walls.

Estimated Completion: May 24, 2012

Macon Project Office-Resident Engineer Jeff Gander

Route D - Safe and Sound Bridge replacement at Little Wyaconda River east of Fairmont

Work Zone Info: ROAD CLOSED detour over Routes W and A .

Project Status: 65% complete-Working on laying asphalt approaches and pouring barrier walls

Estimated Completion: May 30, 2012

Macon Project Office-Resident Engineer Jeff Gander

Route D - Safe and Sound Bridge replacement at Wyaconda River south of Kahoka - Bridge to close May 29, 2012 for 58 days

Work Zone Info: Inactive - Road to be closed May 29 with detour over Routes 81, M and Lewis Route E

Project Status: 0% complete- Bridge to close for demolition May 29, weather permitting.

Estimated Completion: July 20, 2012

Macon Project Office-Resident Engineer Jeff Gander

Maintenance


Route HH
– May 24 traffic reduced to one lane for pavement repairs from 8 a.m. to 3 p.m. from Route Y south to the end of State Maintenance; traffic reduced to one lane from 8 a.m. to 3 p.m.
Various Routes
- May 24-25 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.

Back to Top

Knox County

Construction

Route M - Safe and Sound Bridge replacement at Middle Fabius River south of Rutledge near the Community of Millport - Bridge to close for 58 days

Work Zone Info: Inactive - Road to be closed June 19 with detour over Routes V and K

Project Status: 0% complete- Demolition begins June 19, weather permitting.

Estimated Completion: August 8, 2012

Macon Project Office-Resident Engineer Jeff Gander

Maintenance

Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone

Back to Top

Lewis County

Construction

MO 16 - Safe and Sound Bridge replacement at Sugar Creek east of Monticello - Bridge to close June 5, 2012 for 49 days

Work Zone Info: Inactive - Road to be closed June 5 with detour over Routes F, E and A

Project Status: 0% complete- Bridge to close for demolition June 5, weather permitting.

Estimated Completion: July 23, 2012

Macon Project Office-Resident Engineer Jeff Gander

 

Maintenance

Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.

Back to Top

Lincoln County

Construction Projects

MO 79 - Bridge project at Sandy Creek 1 mile north of Route Y at Foley

Work Zone Info: Road to close July 15

Detour Local and Tourist Traffic on Routes Y, W and B

Detour Option Commercial Traffic on MO 47, US 61 and Route B

Project Status: 0% complete- Road to be closed from July 15-Oct. 1

Estimated Completion: October 2012

Troy Project Office-Resident Engineer Rick Domzalski

MO 47 - Resurface driving lanes and shoulders from west of Route J to Main St. in Troy

Work Zone Info: Nighwork 8 p.m. to 5 a.m. with one lane traffic and flaggers

Project Status: 0% complete- Resurfacing in progress.

Estimated Completion: end of June 2012

Troy Project Office-Resident Engineer Rick Domzalski

US 61 - Resurface northbound lanes and shoulders from just north of Route Z to just south of Route K, 9.5 miles

Work Zone Info: Inactive - One lane traffic beginning June 22-July 31.

Project Status: 0% complete- Milling operations June 22-July 12; paving operations for July 13-July 31.

Estimated Completion: August 9

Troy Project Office-Resident Engineer Rick Domzalski

US 61 - Pavement repair and resurfacing north and southbound lanes from just north of Route OO in Pike Co. to Route B in Lincoln Co., 13.2 miles

Work Zone Info: Inactive - One lane traffic beginning June 5-July 3.

Project Status: 0% complete- Milling operations June 5-12; paving operations scheduled for June 13-20.

Estimated Completion: July 3

Troy Project Office-Resident Engineer Rick Domzalski

Route A - Seal coat from Route DD to Interstate 70 in Warren Co., 12.9 miles

Work Zone Info: Inactive - One lane traffic May 30-June 1.

Project Status: 0% complete-Seal coat begins May 30-June 1.

Estimated Completion: Summer 2012

Troy Project Office-Resident Engineer Rick Domzalski

Route JJ - Seal coat from Route W south junction to MO 79, 8 miles

Work Zone Info: Inactive - One lane traffic June 13-14.

Project Status: 0% complete-Seal coat begins June 13-14.

Estimated Completion: Summer 2012

Troy Project Office-Resident Engineer Rick Domzalski

Route B - Seal coat from US 61 to MO 79, 10.2 miles

Work Zone Info: Inactive - One lane traffic June 15-19.

Project Status: 0% complete-Seal coat begins June 15-19.

Estimated Completion: Summer 2012

Troy Project Office-Resident Engineer Rick Domzalski

Route OO - Seal coat from Route C to end of state maintenance near Chain of Rocks, 1.8 miles

Work Zone Info: Inactive - One lane traffic May 31 - June 1.

Project Status: 0% complete-Seal coat begins May 31-June 1.

Estimated Completion: Summer 2012

Troy Project Office-Resident Engineer Rick Domzalski

Maintenance

Route U – May 24-25 traffic reduced to one lane for pavement repairs from 8 a.m. to 4 p.m. from US 61 south of Moscow Mills to MO 47 south of Hawk Point
Route AA – May 29 traffic reduced to one lane for pavement repairs from 8 a.m. to 4 p.m. from MO 47 between Hawk Point and Troy north to the end of State Maintenance
MO 47 - May 29-30 traffic reduced to one lane for pavement repairs from 8 a.m. to 4 p.m. from just west of US 61 at Troy west to Hawk Point
Route D - May 31 traffic reduced to one lane for pavement repairs from 8 a.m. to 4 p.m. from Route O at Olney to Route E
Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.



Back to Top

Macon County

Maintenance


Route 36 & 63 – May 24-25 mowing; traffic reduced to one lane, 6:30 a.m. to 5:00 p.m.


Back to Top

Marion County

Construction

MO 168 – Bridge replacement over North River 1.4 miles west of Route C near Palmyra.

Work Zone Info: ROAD CLOSED. Detour over Routes C, Z and 168

Project Status: 5% complete - Demolition of old bridge continues and will work on coring drilled shafts.

Estimated Completion: fall 2012

Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln


US 24/61 Palmyra – Intersection improvements at Palmyra from Main Cross St. to Thompson St.
Work Zone Info: Inactive. One lane traffic through work zone area.

Project Status: 0% complete - Inactive. Project has not been scheduled.

Estimated Completion: October 2012

Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln

Maintenance

Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.

Back to Top

Monroe County

Construction Projects

Routes 107 and FF - Preventative maintenance on Mark Twain Lake bridges over North Fork and South Fork Salt River on Route 107, and North Fork Salt River Bridge on Route FF; substructure repairs and modifications, expansion joint replacement, removal and replacement of asphalt surface and upgrading the existing guardrail. Contractor- PCI Roads, LLC.

Project Status: 89% complete - OPEN TO TRAFFIC with one lane traffic on MO 107 for painting and asphalt work at various times.

Macon Project Office-Resident Engineer Jeff Gander

Route CC - Safe and Sound Bridge replacement at Clear Creek south of Shelbina

Project Status: COMPLETED - OPEN TO TRAFFIC

Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln

US 24 - Resurface driving lanes from Randolph County line to just east of Route 15 near Paris

Work Zone Info: One lane traffic

Project Status: 11% complete-Resurfacing with one lane traffic near Paris.

Estimated Completion: Summer 2012

Macon Project Office-Resident Engineer Jeff Gander

Maintenance:

Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.

Back to Top

Montgomery County

Construction Projects:

MO 161 - Safe and Sound Bridge replacement at Elkhorn Creek east of Montgomery City - Bridge to close May 21, 2012 for 49 days

Work Zone Info: Inactive - Road to be closed May 21 with detour over MO 19 and Route CC.

Project Status: 0% complete- Road to be closed at bridge May 21 for demolition to begin, weather permitting.

Estimated Completion: July 9, 2012

Troy Project Office-Resident Engineer Rick Domzalski

MO 94 – Seal coat from MO 19 to Route T at Augusta near the Warren/St. Charles Co. line, 32.670 miles.

Work Zone Info: Inactive -One lane traffic

Project Status: 0% complete-Seal coat to be scheduled at a later date.

Estimated Completion: Summer 2012

Troy Project Office-Resident Engineer Rick Domzalski

Route K – Seal coat from Route D in Callaway County to the Montgomery County line, 5.885 miles.

Work Zone Info: Inactive - One lane traffic

Project Status: 0% complete-Seal coat to be scheduled at a later date.

Estimated Completion: Summer 2012

Troy Project Office-Resident Engineer Rick Domzalski

Route D – Seal coat from I-70 at Williamsburg in Callaway County to MO 94 east of Portland near the Montgomery County line, 18.336 miles.

Work Zone Info: Inactive - One lane traffic

Project Status: 0% complete-Seal coat to be scheduled at a later date.

Estimated Completion: Summer 2012

Troy Project Office-Resident Engineer Rick Domzalski

Maintenance

Various Routes - May 24-25 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone

Back to Top

Pike County

Construction Projects:

Route D - Safe and Sound Bridge replacement at Little Calumet Creek just south of Route N near Calumet - Bridge to close May 7, 2012 for 58 days

Work Zone Info: ROAD CLOSED with detour over MO 79 and Routes N, W and WW.

Project Status: 10% complete- Contractor plans to pour footings and columns on the intermediate bents, weather permitting.

Estimated Completion: June 30, 2012

Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln

US 54 - Safe and Sound Bridge replacement at Noix Creek between Bowling Green and Louisiana- Bridge to close June 18, 2012 for 50 days

Work Zone Info: Inactive - June 18 road to be closed

Commercial Vehicle Detour - Recommended Detour Routes over US 54, MO 79 south, Route B west, US 61 North or South

Local and Tourism Detour - Recommended Detour Routes over US 54, Route UU, US 61 North or South

Project Status: 0% complete- Road to be closed at bridge June 18 for demolition to begin, weather permitting.

Estimated Completion: August 7, 2012

Troy Project Office-Resident Engineer Rick Domzalski

US 54 - Safe and Sound Bridge replacement at North Fork of Noix Creek between Bowling Green and Louisiana- Bridge to close June 25, 2012 for 40 days

Work Zone Info: Inactive - June 25 road to be closed

Commercial Vehicle Detour - Recommended Detour Routes over US 54, MO 79 south, Route B west, US 61 North or South

Local and Tourism Detour - Recommended Detour Routes over US 54, Route UU, US 61 North or South

Project Status: 0% complete- Road to be closed at bridge June 25 for demolition to begin, weather permitting.

Estimated Completion: August 4, 2012

Troy Project Office-Resident Engineer Rick Domzalski

Route UU - Resurface from US 61 near Bowling Green to US 54 near Louisiana

Project Status: COMPLETED - ALL LANES OPEN TO TRAFFIC

Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln

MO 79 - Seal coat from Ralls County line to Route TT near Ashburn.

Work Zone Info: Inactive - Work tentatively scheduled to begin after May 1.

Project Status: 0% complete- Inactive

Estimated Completion: Summer 2012

Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln

Route Z - Seal coat from Route 161 to US 61 in Pike and Lincoln Counties, 16.9 miles

Work Zone Info: Inactive - One lane traffic May 23-31.

Project Status: 0% complete-Seal coat begins May 23 thru 31.

Estimated Completion: Summer 2012

Troy Project Office-Resident Engineer Rick Domzalski

Route H - Seal coat from Route W south junction to MO 79, 3.9 miles

Work Zone Info: One lane traffic May 22.

Project Status: 0% complete-Seal coat begins May 22.

Estimated Completion: Summer 2012

Troy Project Office-Resident Engineer Rick Domzalski

US 61 - Pavement repair and resurfacing north and southbound lanes from just north of Route OO in Pike Co. to Route B in Lincoln Co., 13.2 miles

Work Zone Info: Inactive - One lane traffic beginning June 12.

Project Status: 0% complete- Milling and paving operations scheduled to begin June 12.

Estimated Completion: July 3

Troy Project Office-Resident Engineer Rick Domzalski

Maintenance


Various Routes
- May 24-25 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.


Back to Top

Ralls County

Construction Projects:

MO 19 - Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles.

Work Zone Info: Inactive - Job has not been scheduled

Project Status: 0% complete- A preconstruction conference will be scheduled to determine the start date.

Estimated Completion: Summer 2012

Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln

Route T - Resurface from just south of MO 79 to Route N south of Hannibal .

Work Zone Info: Inactive - Work tentatively scheduled to begin June 1.

Project Status: 0% complete- Inactive

Estimated Completion: Fall 2012

Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln

MO 154 - Resurface from MO 19 to US 54 near Hutchison between Curryville and Vandalia.

Work Zone Info: Inactive

Project Status: 0% complete-Resurfacing to begin in June.

Estimated Completion: Summer 2012

Macon Project Office-Resident Engineer Jeff Gander

Route E - Seal coat from MO 79 to end of State maintenance near Saverton.

Work Zone Info: Inactive - Work tentatively scheduled to begin after May 1.

Project Status: 0% complete- Inactive

Estimated Completion: Summer 2012

Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln

Route T - Seal coat from Route N south of Hannibal to MO 79 near Ashburn .

Work Zone Info: Inactive - Work tentatively scheduled to begin June 1.

Project Status: 0% complete- Inactive

Estimated Completion: Summer 2012

Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln

Route V - Seal coat from Ralls Street in New London to Route T.

Work Zone Info: Inactive - Work tentatively scheduled to begin after May 1.

Project Status: 0% complete- Inactive

Estimated Completion: Summer 2012

Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln

Route N - Seal coat from Route T to MO 79 near Saverton.

Work Zone Info: Inactive -Work tentatively scheduled to begin after May 1.

Project Status: 0% complete- Inactive

Estimated Completion: Summer 2012

Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln

Maintenance

Various Routes - May 24-25 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.

Back to Top

Randolph County

Construction Projects

Route B - Resurfacing from Route A to US 63 near Clark, 8.541 miles

Work Zone Info: One lane traffic with 45 mph work zone speed limit from 6:30 a.m. to 8 p.m.. while crews are present.

Project Status: 64% complete-Paving operation to begin May 22 or 23.

Estimated Completion: Summer 2012

Macon Project Office-Resident Engineer Jeff Gander

Route M - Resurfacing from US 63 in Moberly to MO 151 at the Monroe county line, 10.869 miles

Work Zone Info: One lane traffic with 45 mph work zone speed limit from 6:30 a.m. to 8 p.m.. while crews are present.

Project Status: 64% complete-Paving operations in progress.

Estimated Completion: Summer 2012

Macon Project Office-Resident Engineer Jeff Gander

MO 3 - Resurfacing from Route T to north of US 24 near Clifton Hill, 12.721 miles

Project Status: COMPLETED-ALL LANES OPEN TO TRAFFIC

Macon Project Office-Resident Engineer Jeff Gander

Maintenance


Route AA – May 24-25 extensive pavement repairs; traffic reduced to one lane from Rte B to Rte A, 7:00 a.m. to 3:30 p.m.

Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.

Back to Top

Schuyler County

Maintenance

Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.

Back to Top

Scotland County

Maintenance

Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.

Back to Top

Shelby County

See Route 36 Four-Lane Webpage

Construction Projects:

Route H - Safe and Sound Bridge replacement at Hilton Branch south of Leonard - Bridge to close May 7, 2012 for 39 days

Work Zone Info: ROAD CLOSED with detour over MO 151 and Route K .

Project Status: 50% complete- Contractor plans to grout, post tension and possibly pour barrier wall, weather permitting.

Estimated Completion: May 30, 2012

Macon Project Office-Resident Engineer Jeff Gander

MO 151 - Safe and Sound Bridge replacement at Otter Creek south of Clarence - Bridge to close May 31, 2012 for 45 days

Work Zone Info: Inactive - Road to be closed May 31 with detour over US 36, and Routes TT and DD .

Project Status: 0% complete- Road to be closed at bridge May 31 for demolition to begin, weather permitting.

Estimated Completion: July 15, 2012

Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln

MO 15 Install guardrail near Elm Street at US 36 interchange at Shelbina

Work Zone Info: Inactive. One lane traffic through work zone area.

Project Status: 0% complete - Inactive. Project has not been scheduled.

Etimated Completion: October 2012

Macon Project Office-Resident Engineer Jeff Gander

Maintenance

Various Minor Routes - May 24-June 1 mowing; traffic reduced to one lane with blocker truck at the work zone.

Back to Top

Warren County

Construction Projects:

Route A - Safe and Sound Bridge replacement at Camp Creek east of Truxton

Work Zone Info: ROAD CLOSED detour over MO 47 and Routes W and A.

Project Status: 80% complete-Contractor plans to work on barrier curbs and place guardrail and finish dirt work, weather permitting.

Estimated Completion: May 25, 2012

Troy Project Office-Resident Engineer Rick Domzalski

I-70 eastboundResurface driving lanes and shoulders from the St. Charles Co. line to Wright City

Work Zone Info: Night work with one lane traffic from 7 p.m. to 5 a.m.

Project Status: 0% complete- Resurfacing in progress.

Estimated Completion: July 2012

Troy Project Office-Resident Engineer Rick Domzalski

MO 94 – Seal coat from MO 19 to Route T at Augusta near the Warren/St. Charles Co. line, 32.670 miles.

Work Zone Info: Inactive - One lane traffic

Project Status: 0% complete-Seal coat to be scheduled at a later date.

Estimated Completion: Summer 2012

Troy Project Office-Resident Engineer Rick Domzalski

Route MM - Resurface from Old 40 to Route M at Warrenton

Work Zone Info: Inactive

Project Status: 0% complete- Milling and resurfacing operations to be scheduled at a later date.

Estimated Completion: Summer 2012

Troy Project Office-Resident Engineer Rick Domzalski

Route AA - Resurface from Route 47 to the end of state maintenance

Work Zone Info: Inactive

Project Status: 0% complete- Milling and resurfacing operations to be scheduled at a later date.

Estimated Completion: Summer 2012

Troy Project Office-Resident Engineer Rick Domzalski

Route H - Seal coat from just south of I-70 to Route M, 3.6 miles

Work Zone Info: Inactive - One lane traffic June 4.

Project Status: 0% complete-Seal coat begins June 4.

Estimated Completion: Summer 2012

Troy Project Office-Resident Engineer Rick Domzalski

Route W- Seal coat from Warrenton north to Route A, 10.2 miles

Work Zone Info: Inactive -One lane traffic

Project Status: 0% complete-Seal coat to be scheduled at a later date

Estimated Completion: Summer 2012

Troy Project Office-Resident Engineer Rick Domzalski

Maintenance

Route N – May 24 traffic reduced to one lane for pavement repairs from 8 a.m. to 4 p.m. from MO 47 to MO 94 at Treloar
Route CC – May 29 traffic reduced to one lane for pavement repairs from 8 a.m. to 4 p.m. from MO 47 south of Warrenton to the end of State Maintenance
Route F – May 30 traffic reduced to one lane for pavement repairs from 8 a.m. to 4 p.m. from Wright City to the end of State Maintenance near Innsbrook

Various Routes - May 24-25 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.


Back to Top
 
   
   