| Safe & Sound Online Map -- Check bridge projects and detours in your area |
| |
|
RFQ & DRAFT RFP NOW POSTED UNDER PROGRAM DOCUMENTS |
|
| |
|
The Missouri Department of Transportation’s Safe & Sound Bridge Improvement Program is a two-phase program to improve 802 of the state’s lowest-rated bridges by Oct. 31, 2014.
Some 248 bridges have been identified for rehabilitation, and at least 100 of those will be under construction in Spring 2009. They are being put out for bid in groups according to location, type or size to expedite the design and construction process.
The other 554 bridges are scheduled for replacement and have been packaged in a single Design-Build contract. The procurement process to select a team to perform the work has begun.
Important Procurement Dates
Oct. 27, 2008 Issue RFQ
Oct. 30, 2008 Industry Review Meeting
Dec. 3, 2008 Receive SOQs
Dec. 16, 2008 Shortlist Teams
March 25, 2009 Initial Technical Proposals Due
April 28, 2009 Final Technical Proposals & Price Allocation Due
May 1, 2009 Select Team
May 2009 Award Contract |
|
Contact us at safeandsound@modot.mo.gov
Media desiring additional information, please contact: Bob Brendel at 573-751-8717
The documents are provided in Acrobat Reader format. Free Acrobat Reader download 