Click here for the major work planned in 2008 (listed by county).
All work is subject to change due to weather or priority adjustments.
Receive email updates on roadwork projects

Counties:
Barry County
Maintenance Activities
Route 60 - March 31-late 2008 - Grading, drainage and bridge work from Route 37/60 to just east of Bridle Lane in Monett. Traffic was moved onto the new bridge Sept. 19.
Route B - Sept. 30-Oct. 17 - Laying blacktop from Route 97 to Route 37.
Routes 90, M and E - Oct. 6-10 - Pavement repairs.
Route 39 - Oct. 7 - Installing signs at the Table Rock bridge.
Various routes - Oct. 6-10 - Mowing and maintaining signs.
Back to Top
Barton County
Maintenance Activities
Route 160 - Oct. 6-10 - Grinding humps.
Various routes - Oct. 6-10 - Mowing, patching pavement and maintaining signs.
Back to Top
Bates County
Maintenance Activities
Various routes - Oct. 6-10 - Mowing.
Back to Top
Cedar County
Maintenance Activities
Route 245 - Sept. 29-Oct. 31 - Repairing the Route 245 bridge over Stockton Lake at the Dade/Cedar County line. Motorists should expect lane closures for the next month, but delays should be minimal.
Route 82 - Oct. 6-9 - Repairing shoulders at Route EE, and replacing curb and gutter at the corner of Olive Street. Motorists should expect one-lane traffic throughout the week with delays of up to five minutes.
Various routes - Oct. 6-10 - Mowing and replacing signs.
Back to Top
Dade County
Maintenance Activities
Route 245 - Sept. 29-Oct. 31 - Repairing the Route 245 bridge over Stockton Lake at the Dade/Cedar County line on Monday, Sept. 29. Motorists should expect lane closures for the next month, but delays should be minimal.
Various routes - Oct. 6-10 - Mowing and maintaining signs.
Back to Top
Jasper County
Construction Activities
Route 249 - APAC-Missouri, Inc. - Building four-lane highway from I-44 to Route 171 in Carterville.
Opening and Ribbon-Cutting Ceremony - Monday, Oct. 6, 9 a.m.
Route 171 - APAC-Missouri, Inc. - Building temporary crossover for construction on Route 249.
Estimated completion - Fall 2008
Maintenance Activities
Various routes - Oct. 6-10 - Mowing and laying asphalt.
Back to Top
Lawrence County
Construction Activities
Business 60 - Journagan Construction Co., Inc. - Resurfacing from Routes 37/60 to just east of Bridle Lane in Monett.
Location - Through Aurora.
Estimated completion - Dec. 1, 2008
Maintenance Activities
Route 265 - Sept. 23-Oct. 9 - Patching pavement at Route 60.
Business 60 - Oct. 2-7 - Pavement repairs from Wolfe Road to Route 60.
Route H - Sept. 23-Oct. 9 - Patching pavement near Cleveland Street.
Route V V - Sept. 23-Oct. 9 - Repairing pavement near Route 37.
Route 96 and I-44 - Oct. 6-10 - Paving shoulders.
Various routes - Oct. 6-10 - Mowing.
Back to Top
McDonald County
Maintenance Activities
Route K - Oct. 1-9 - Repairing shoulders from Business 71 to Route 90.
Route 71 - Oct. 6-Nov. 3 - Resurfacing at Business 71.
Various routes - Oct. 6-10 - Mowing.
Back to Top
Newton County
Maintenance Activities
Route W - Oct. 6 - Resurfacing from Route M to Route J.
Routes W, EE, Y and DD - Sealing pavement.
Various routes - Oct. 6-10 - Mowing.
Back to Top
St.Clair County
Maintenance Activities
Route 54 - Aug. 26-Oct. 31 - Resurfacing from Route 123 to Route 83.
Route 13 - July 14-Oct. 20 - Building new lanes near Route B.
Route 82 - Sept. 29-Oct. 6 - Repairing shoulders from Route U to Route 13.
Route B - Sept. 29-Oct. 6 - Repairing shoulders near Route E.
Back to Top
Vernon County
Maintenance Activities
Route 71 - Sept. 26-Oct. 24 - Resurfacing from Highland Ave. to Route E.
Various routes - Oct. 6-10 - Mowing.
Back to Top