Southern Jefferson County Update
WHAT'S HAPPENING IN 2008?
- Route 21 between Hayden Road and Lake Lorraine - Construction is underway and is expected to be complete in early 2009.
*MoDOT has completed the section of Route 21 between Hayden Road and Route A in 2007. Due to safety concerns, MoDOT will only open the southbound lane of Route 21 between Hayden Road and Route A in approximately June 2008.
- I-55 Guard Cable - Install guard cable in the median of I-55 in all the remaining gap areas along the interstate between Route M and Route 67. Construction is expected to be complete by May 2008.
- Various locations on Route BB - Replace the culverts. Construction has begun.
- Route BB at Baker School - Realign the curve. Construction has begun.
- Route BB at Sand Creek - Replace the bridge, which is expected to close in March 2008.
FUTURE PROJECTS:
- Various locations on Route P - Replace the culverts. Construction is expected to begin in early 2009.
For more information, contact:
Contact MoDOT Area Engineer Judy Wagner at 1-888 ASK MODOT (275-6636) or e-mail Judy.Wagner@modot.mo.gov
Contact MoDOT Community Relations Specialist Kara Price at 1-888 ASK MODOT (275-6636) or e-mail Kara.Price@modot.mo.gov
|